Private Corporate Event – Arena Rigging Installation Feb 2026
Client: Private Corporate Client
Venue: 3Arena
Event Type: Corporate / Live Production
Timing: February 2026
Services Provided: Rigging supervision, labour supply, spreader truss provision & certification
Overview
One Event Infrastructure delivered large-scale production rigging services for a private corporate event within the 3Arena, Dublin.
The project involved the installation of over 140 rigging points across the arena roof structure, including areas not previously rigged for live production.
Works required close coordination with venue technical teams and the integration of IRATA-certified rescue support due to off-grid climbing and beam access.
Scale at a Glance
Within the 3Arena roof structure, One Event Infrastructure delivered:
140+ rigging points installed
Installation across closed grid and off-grid beam locations
Spreader truss provision where required
IRATA-certified rescue team integrated into works
Crew deployment reflected the scale and complexity of the installation:
15 riggers deployed during primary day builds
9–15 riggers deployed across night and follow-on shifts
Multi-day installation and load-out phases supported by large arena-experienced crews
All rigging was installed, inspected, and formally handed over in accordance with approved RAMS and industry best practice.
Programme & Delivery
The works were delivered across load-in, show period and load-out phases in line with the agreed production schedule.
Delivery required:
Advance coordination with 3Arena technical management
Installation in roof areas not previously utilised for production rigging
Off-grid climbing and beam access
Implementation of exclusion zones and controlled work areas
Daily Dynamic Risk Assessments prior to each shift
IRATA-certified rescue riggers were present for all high-risk access works.
What We Delivered
Rigging supervision under an appointed Head Rigger
Installation of rigging points using dead hangs, bridles and spreader truss
Coordination with touring production and venue teams
Visual inspection and structured handover
Formal rigging completion certification
Our Approach
Delivery focused on competence, control and collaboration.
Key priorities included:
Deploying experienced arena riggers familiar with 3Arena roof systems
Coordinating access methods between closed grid, MEWP and off-grid climbing
Maintaining strict supervision and communication
Ensuring all works were delivered under an approved RAMS framework
Integrating third-party IRATA rescue provision where required
Outcome
The installation was completed safely, to programme, and in accordance with venue requirements.
The project was completed with:
Over 140 rigging points installed
Full compliance with approved RAMS
IRATA rescue provision integrated throughout
Formal completion certification issued
Key Takeaway
Complex arena rigging requires experience, planning, and coordination across production, venue, and specialist access teams.
This project demonstrates One Event Infrastructure’s capability to deliver high-volume rigging installations in technically demanding arena environments.